97 works across 1 implementing agency, recommended by 7 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) 1 high risk | 97 | 21 | ₹5.15 Cr | 16 | 24.1 | guddi devi 7% of spend · 326 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Sanjna Jatav BHARATPUR | 82 | ₹4.08 Cr | 7 |
| Ghanshyam Tiwari Sitting Rajya Sabha | 4 | ₹24.93 L | 2 |
| Mukul Wasnik Sitting Rajya Sabha | 3 | ₹20.00 L | 2 |
| Pramod Tiwari Sitting Rajya Sabha | 3 | ₹15.50 L | 1 |
| Sonia Gandhi Sitting Rajya Sabha | 2 | ₹20.00 L | 2 |
| Randeep Singh Surjewala Sitting Rajya Sabha | 2 | ₹20.00 L | 2 |
| Madan Rathore Sitting Rajya Sabha | 1 | ₹6.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 56 | ₹3.10 Cr | 12 |
| Water | 12 | ₹20.49 L | 0 |
| Community Buildings | 11 | ₹85.99 L | 1 |
| Education | 6 | ₹37.41 L | 2 |
| Religious & Cultural | 5 | ₹33.98 L | 1 |
| Street Lighting | 3 | ₹4.98 L | 0 |
| Other | 1 | ₹1.70 L | 0 |
| Drainage & Sanitation | 1 | ₹5.00 L | 0 |
| Health | 1 | ₹9.94 L | 0 |
| Boundary & Protection | 1 | ₹5.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Community Hall at Near Toda Mandir, Village ₹999,991 against a ₹500,000 median for Community Buildings works in BHARATPUR (100% above, 19 peer works) | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹10.00 L | 142 d | +100% | 70.5 | HIGH |
| Construction of Rooms at Rajkiya Uchhatar Madhyamik Vidyalay ₹1,000,000 against a ₹543,486 median for Education works in BHARATPUR (84% above, 14 peer works) | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹10.00 L | 142 d | +84% | 66.5 | MEDIUM |
| INTERLOCKING BRICK KHARANJA WORK IN BAGHEL BASTI, VILLAGE BA 709 days beyond expected completion | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹5.00 L | 709 d | +0% | 60.7 | MEDIUM |
| INTERLOCKING BRICK KHARANJA WORK FROM RADHAKRISHAN TEMPLE TO 709 days beyond expected completion | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹5.00 L | 709 d | +0% | 60.7 | MEDIUM |
| Interlocking Bricks Kharanja Road cum Drain/Sewer works from 335 days beyond expected completion | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹5.00 L | 335 d | +0% | 59.5 | MEDIUM |
| Construction of Bricks Road with drainage from Pratp Shop to ₹1,000,000 against a ₹499,834 median for Roads & Paving works in BHARATPUR (100% above, 124 peer works) | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹10.00 L | 42 d | +100% | 56.6 | MEDIUM |
| Interlocking bricks kharanja may nali Nirman karya bugli ke 375 days beyond expected completion | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹4.00 L | 375 d | -20% | 54.7 | MEDIUM |
| Interlocking bricks kharanja May nali Nirman karya Leela pat 375 days beyond expected completion | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹3.00 L | 375 d | -40% | 54.2 | MEDIUM |
| Construction Of CC Road From Reham House To Kishni Ke Nohre ₹1,000,000 against a ₹499,834 median for Roads & Paving works in BHARATPUR (100% above, 124 peer works) | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹10.00 L | — | +100% | 50.8 | MEDIUM |
| For construction work of drain with interlocking tiles in Si ₹1,499,750 against a ₹499,834 median for Roads & Paving works in BHARATPUR (200% above, 124 peer works) | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Completed | ₹15.00 L | — | +200% | 50.8 | MEDIUM |
| Construction of well furnished Library Room in Freedom Fight ₹1,000,000 against a ₹543,486 median for Education works in BHARATPUR (84% above, 14 peer works) | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹10.00 L | — | +84% | 46.8 | MEDIUM |
| interlocking bricks kharnja nirman karya mali ki kuiya se ku ₹800,000 against a ₹499,834 median for Roads & Paving works in BHARATPUR (60% above, 124 peer works) | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹8.00 L | 273 d | +60% | 46.4 | MEDIUM |
| Suraksha Deewar shamshan Ghat bhadeera work agency GP bhadee 375 days beyond expected completion | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹6.00 L | 375 d | +20% | 40.8 | MEDIUM |
| Interlocking sadak Nirman karya mukhya sadak se atar Singh j 375 days beyond expected completion | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹6.00 L | 375 d | +20% | 40.8 | MEDIUM |
| Rajkiya uchch madhyamik vidyalaya parisar mein interlocking 375 days beyond expected completion | BHARATPUR(DISTRICT COLLECTOR BHARATPUR_IDA) | Recommended | ₹6.00 L | 375 d | +20% | 40.8 | MEDIUM |