69 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | 69 | 9 | ₹8.28 Cr | 31 | 38.1 | JAY HANUMAN TRADERS 13% of spend · 41 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Rajkumar Roat BANSWARA | 31 | ₹4.73 Cr | 12 |
| Chunnilal Garasiya Sitting Rajya Sabha | 26 | ₹2.46 Cr | 14 |
| Mukul Wasnik Sitting Rajya Sabha | 8 | ₹79.78 L | 4 |
| Randeep Singh Surjewala Sitting Rajya Sabha | 3 | ₹20.00 L | 0 |
| Pramod Tiwari Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 27 | ₹2.73 Cr | 9 |
| Education | 17 | ₹3.27 Cr | 8 |
| Community Buildings | 12 | ₹99.00 L | 6 |
| Religious & Cultural | 8 | ₹69.79 L | 5 |
| Sports | 2 | ₹30.00 L | 2 |
| Water | 1 | ₹15.00 L | 0 |
| Equipment & Vehicles | 1 | ₹5.00 L | 0 |
| Boundary & Protection | 1 | ₹10.00 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Khulli Baradari (Baramda) in Gram Panchayat ₹1,000,000 against a ₹600,000 median for Community Buildings works in BANSWARA (67% above, 39 peer works) | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹10.00 L | 558 d | +67% | 67.6 | MEDIUM |
| Block Stariya Library Bhavan Nirman Kary ₹2,500,000 against a ₹1,350,000 median for Education works in BANSWARA (85% above, 26 peer works) | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹25.00 L | 143 d | +85% | 67.1 | MEDIUM |
| Block Stariya Library Bhavan Nirman Kary ₹2,500,000 against a ₹1,350,000 median for Education works in BANSWARA (85% above, 26 peer works) | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹25.00 L | 143 d | +85% | 67.1 | MEDIUM |
| Someshwar Mahadav in Jhupel for the construction of Khuli Ba Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹10.00 L | 583 d | +2% | 63.5 | MEDIUM |
| community building construction work
Construction work of co Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹10.00 L | 338 d | +2% | 62.7 | MEDIUM |
| Valley cutting through gravel road (Charkani to Gad Ki and G Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹10.00 L | 294 d | 0% | 61.9 | MEDIUM |
| Valley cutting on gravel road from Limdiwali Mali to Kuvesia Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹10.00 L | 294 d | 0% | 61.9 | MEDIUM |
| open community building construction
Open Baradari construc 338 days beyond expected completion | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹5.00 L | 338 d | -49% | 59.6 | MEDIUM |
| open community construction work
Motira near Mataji Temple 338 days beyond expected completion | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹5.00 L | 338 d | -49% | 59.6 | MEDIUM |
| boundary wall extension construction work
Four wall extensio 338 days beyond expected completion | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹5.00 L | 338 d | -63% | 59.6 | MEDIUM |
| Construction of Grewal Road cum Ghatakating from Charkali De 558 days beyond expected completion | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹5.00 L | 558 d | -50% | 59.0 | MEDIUM |
| Construction of Grewal Road in Gram Panchayat Pali Chhoti, P 558 days beyond expected completion | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹5.00 L | 558 d | -50% | 59.0 | MEDIUM |
| Construction of CC Road from the house of Mansingh to Anganw 127 days beyond expected completion | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹10.00 L | 127 d | 0% | 52.1 | MEDIUM |
| Classroom construction, Vidya Niketan School Kothara (Vidya ₹2,500,000 against a ₹1,350,000 median for Education works in BANSWARA (85% above, 26 peer works) | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹25.00 L | 31 d | +85% | 51.5 | MEDIUM |
| banswara ward no 1 piplod mein samudayik bhavan nimran kary ₹1,000,000 against a ₹600,000 median for Community Buildings works in BANSWARA (67% above, 39 peer works) | BANSWARA(DISTRICT COLLECTOR BANSWARA_IDA) | Recommended | ₹10.00 L | 299 d | +67% | 47.6 | MEDIUM |