334 works across 1 implementing agency, recommended by 7 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) 1 high risk | 334 | 48 | ₹20.37 Cr | 18 | 22.3 | ABHIJEET AGENCIES SOLAPUR 35% of spend · 18 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Mohite Patil Dhairyasheel Rajsinh MADHA | 174 | ₹6.21 Cr | 10 |
| Praniti Sushilkumar Shinde SOLAPUR | 131 | ₹11.84 Cr | 1 |
| Omprakash Bhupalsinh Alias Pavan Rajenimbalkar OSMANABAD | 21 | ₹1.41 Cr | 0 |
| Dhananjay Bhimrao Mahadik Sitting Rajya Sabha | 4 | ₹60.00 L | 3 |
| Medha Vishram Kulkarni Sitting Rajya Sabha | 2 | ₹10.00 L | 2 |
| Milind Murli Deora Sitting Rajya Sabha | 1 | ₹5.00 L | 1 |
| Ajeet Madhavrao Gopchade Sitting Rajya Sabha | 1 | ₹16.05 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 151 | ₹3.78 Cr | 9 |
| Community Buildings | 70 | ₹6.77 Cr | 2 |
| Roads & Paving | 51 | ₹4.41 Cr | 2 |
| Religious & Cultural | 25 | ₹2.28 Cr | 0 |
| Sports | 10 | ₹1.21 Cr | 3 |
| Equipment & Vehicles | 8 | ₹66.78 L | 0 |
| Water | 7 | ₹41.47 L | 0 |
| Education | 6 | ₹40.00 L | 2 |
| Other | 2 | ₹10.91 L | 0 |
| Drainage & Sanitation | 2 | ₹14.99 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
An agency whose sanctions all arrive in the last quarter looks identical. This is a spending pattern, not a finding.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Puluj, Tal. Pandharpur, Vyayam Sahala Building Construction ₹2,500,000 against a ₹999,976 median for Sports works in SOLAPUR (150% above, 20 peer works) | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹25.00 L | 423 d | +150% | 71.7 | HIGH |
| Construction of a kindergarten building at Dattanagar Mohol ₹500,000 against a ₹231,000 median for Education works in SOLAPUR (116% above, 29 peer works) | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹5.00 L | 111 d | +116% | 62.1 | MEDIUM |
| Construction of buildings for Vyayamshala in At/po. Suste, T ₹1,500,000 against a ₹999,976 median for Sports works in SOLAPUR (50% above, 20 peer works) | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹15.00 L | 275 d | +50% | 59.5 | MEDIUM |
| Ashti, Tal.Mohol, Dist.Solapur Construction Sabhamandap Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹10.00 L | 414 d | 0% | 58.9 | MEDIUM |
| Construction of community centers and community halls in the ₹1,000,000 against a ₹231,000 median for Education works in SOLAPUR (333% above, 29 peer works) | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹10.00 L | 217 d | +333% | 51.7 | MEDIUM |
| Mohol taluka Penur gav yethe grampanchayat jagevar vyamshala ₹2,000,000 against a ₹999,976 median for Sports works in SOLAPUR (100% above, 20 peer works) | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹20.00 L | 222 d | +100% | 51.7 | MEDIUM |
| Installation of Solar High Mast in Adarshnagar, Dr. Babasahe ₹220,000 against a ₹89,897 median for Street Lighting works in SOLAPUR (145% above, 573 peer works) | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹2.20 L | 165 d | +145% | 49.6 | MEDIUM |
| Installation of Solar High Mast Near Khadak Wasti Magas Wast ₹220,000 against a ₹89,897 median for Street Lighting works in SOLAPUR (145% above, 573 peer works) | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹2.20 L | 165 d | +145% | 49.6 | MEDIUM |
| Installation of Solar High Mast Near Kuber Nursery Chouk, Ap ₹220,000 against a ₹89,897 median for Street Lighting works in SOLAPUR (145% above, 573 peer works) | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹2.20 L | 165 d | +145% | 49.6 | MEDIUM |
| Construction of Cement Concrete Road at Village Moje, Bitarg 120 days beyond expected completion | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹5.00 L | 120 d | -32% | 43.8 | MEDIUM |
| Installation of Solar High Mast near Shri Tambda Maruti Temp Completed work has no photographic documentation on record | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Completed | ₹2.15 L | — | +140% | 42.7 | MEDIUM |
| Installation of Solar High Mast near Shri Maruti Temple, Ap. Completed work has no photographic documentation on record | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Completed | ₹2.15 L | — | +140% | 42.7 | MEDIUM |
| Installation of paver blocks for a kindergarten at Dattanaga 111 days beyond expected completion | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Recommended | ₹5.00 L | 111 d | -32% | 42.5 | MEDIUM |
| Installation of Solar Highmast pole near Satwai Farm, Karmal Completed work has no photographic documentation on record | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Completed | ₹2.15 L | — | +140% | 41.8 | MEDIUM |
| Installation of Solar Highmast pole, at S.T. Colony, near Sa Completed work has no photographic documentation on record | SOLAPUR(DISTRICT COLLECTOR SOLAPUR_IDA) | Completed | ₹2.15 L | — | +140% | 41.8 | MEDIUM |