Open this link on a larger screen to see the verification queue.
93 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | 93 | 41 | ₹9.91 Cr | 1 | 11.1 | UNITY ENTERPRISES 16% of spend · 43 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Anup Sanjay Dhotre AKOLA | 91 | ₹8.89 Cr | 0 |
| Imran Pratapgarhi Sitting Rajya Sabha | 1 | ₹99.99 L | 1 |
| Anil Sukhdeorao Bonde Sitting Rajya Sabha | 1 | ₹2.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 71 | ₹6.68 Cr | 0 |
| Community Buildings | 18 | ₹1.97 Cr | 0 |
| Education | 2 | ₹1.15 Cr | 1 |
| Equipment & Vehicles | 1 | ₹2.00 L | 0 |
| Religious & Cultural | 1 | ₹10.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Smart Boards Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹99.99 L | 216 d | 0% | 68.4 | MEDIUM |
| Construction of Community Hall at Hiwarkhed near Shankar San ₹1,500,000 against a ₹989,120 median for Community Buildings works in AKOLA (52% above, 35 peer works) | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹15.00 L | 164 d | +52% | 37.2 | LOW |
| Construction of Community Hall on Corporation land at Prbhag Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹12.00 L | 164 d | +21% | 34.4 | LOW |
| Construction of Community hall at Matang Vasti Kaulkhed Baha 164 days beyond expected completion | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹10.00 L | 164 d | +1% | 33.3 | LOW |
| Construction of Community Hall on Gram Panchayat land at Piw 164 days beyond expected completion | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹10.00 L | 164 d | +1% | 33.3 | LOW |
| Construction of Bus Stop on Gram Panchayat land at Jambha Kh 164 days beyond expected completion | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹10.00 L | 164 d | +1% | 33.3 | LOW |
| Construction of Community Hall at Nage Layout Hanuman Mandir 164 days beyond expected completion | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹10.00 L | 164 d | +1% | 33.3 | LOW |
| Construction of Cement Road from house of Bhojraj Navel to h 164 days beyond expected completion | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹10.00 L | 164 d | +3% | 33.3 | LOW |
| Construction of Community Hall on Gram Panchayat Land at Hir 164 days beyond expected completion | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹10.00 L | 164 d | +1% | 33.3 | LOW |
| Construction of Community Hall at Ujaleshwar on Gram Panchay 164 days beyond expected completion | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹10.00 L | 164 d | +1% | 33.3 | LOW |
| Construction of Community Hall at Sherwadi in Scheduled Trib 164 days beyond expected completion | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹10.00 L | 164 d | +1% | 33.3 | LOW |
| Construction of Community Hall on Gram Panchyat Land near Ha 164 days beyond expected completion | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹10.00 L | 164 d | +1% | 33.3 | LOW |
| Construction of Cement Road at Prabhag 4 Sanjay Nagar Mothi 125 days beyond expected completion | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹10.00 L | 125 d | +3% | 27.3 | LOW |
| Purchase of IT systems at Shri Bagachi vioidyalay Ruikhed ak 100% similarity with another nearby work | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹2.00 L | — | 0% | 21.9 | LOW |
| Construction of community hall at Varangaon on GP land ₹1,500,000 against a ₹989,120 median for Community Buildings works in AKOLA (52% above, 35 peer works) | AKOLA(DISTRICT COLLECTOR AKOLA_IDA) | Recommended | ₹15.00 L | — | +52% | 14.4 | LOW |