117 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | SHAHDOL(District Collector Shahdol_IDA) | 117 | 61 | ₹11.63 Cr | 86 | 41.5 | SADGURU SAI INFRA WORLD PVT LTD REWA 64% of spend · 24 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Rajesh Mishra SIDHI | 61 | ₹7.21 Cr | 60 |
| Himadri Singh SHAHDOL | 54 | ₹4.07 Cr | 25 |
| Vivek K. Tankha Sitting Rajya Sabha | 1 | ₹10.50 L | 0 |
| Sumitra Balmik Sitting Rajya Sabha | 1 | ₹25.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 58 | ₹6.24 Cr | 57 |
| Water | 28 | ₹1.74 Cr | 17 |
| Roads & Paving | 21 | ₹2.24 Cr | 9 |
| Education | 5 | ₹85.00 L | 2 |
| Community Buildings | 2 | ₹25.00 L | 1 |
| Equipment & Vehicles | 1 | ₹10.50 L | 0 |
| Drainage & Sanitation | 1 | ₹10.00 L | 0 |
| Boundary & Protection | 1 | ₹10.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
Round figures are normal and similar works legitimately cost the same. One figure covering nearly every work is what this looks for, and it means the costing is worth seeing, not that it is wrong.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| GRAM PANCHAYAT DARAIN ME JAWARI DHAR NALA ME STOP DAM NIRMAN ₹2,000,000 against a ₹205,055 median for Water works in SHAHDOL (875% above, 67 peer works) | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹20.00 L | 188 d | +875% | 64.0 | MEDIUM |
| GRAM PANCHAYAT TENDUDOL ME CHHULA DHAR NALA ME STOP DAM NIRM ₹2,400,000 against a ₹205,055 median for Water works in SHAHDOL (1070% above, 67 peer works) | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹24.00 L | 188 d | +1070% | 64.0 | MEDIUM |
| GRAM PANCHAYAT JAMUNIHA ANTARGAT GRAM MADHA KOSHTA DHAR ME S ₹1,500,000 against a ₹205,055 median for Water works in SHAHDOL (632% above, 67 peer works) | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹15.00 L | 188 d | +632% | 63.0 | MEDIUM |
| 12 solar street light installation work. Implementing Agency 220 days beyond expected completion | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹3.71 L | 220 d | -68% | 61.8 | MEDIUM |
| 12 solar street light installation work. Implementing Agency 220 days beyond expected completion | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹3.71 L | 220 d | -68% | 61.8 | MEDIUM |
| 12 solar street light installation work. Implementing Agency 220 days beyond expected completion | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹3.71 L | 220 d | -68% | 61.8 | MEDIUM |
| 12 solar street light installation work. Implementing Agency 220 days beyond expected completion | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹3.71 L | 220 d | -68% | 61.8 | MEDIUM |
| 12 solar street light installation work. Implementing Agency 220 days beyond expected completion | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹3.71 L | 220 d | -68% | 61.8 | MEDIUM |
| 12 solar street light installation work. Implementing Agency 220 days beyond expected completion | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹3.71 L | 220 d | -68% | 61.8 | MEDIUM |
| GRAM PANCHAYAT BASOHARA ME JHUNKIYA NALA ME MEENA KEWAT KE G ₹1,500,000 against a ₹205,055 median for Water works in SHAHDOL (632% above, 67 peer works) | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹15.00 L | 188 d | +632% | 59.7 | MEDIUM |
| Room Construction work in Bus stand commercial complex. Impl ₹1,500,000 against a ₹66,256 median for Community Buildings works in SHAHDOL (2164% above, 8 peer works) | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹15.00 L | 228 d | +2164% | 59.7 | MEDIUM |
| Culvert and Returning wall construction work in Mairtola ac ₹2,499,000 against a ₹1,000,000 median for Roads & Paving works in SHAHDOL (150% above, 27 peer works) | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹24.99 L | 322 d | +150% | 59.7 | MEDIUM |
| GI water tanker capacity 5000 liters with water filter plant ₹480,118 against a ₹205,055 median for Water works in SHAHDOL (134% above, 67 peer works) | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹4.80 L | — | +134% | 54.7 | MEDIUM |
| GI water tanker capacity 5000 liters with water filter plant ₹480,118 against a ₹205,055 median for Water works in SHAHDOL (134% above, 67 peer works) | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹4.80 L | — | +134% | 54.7 | MEDIUM |
| GI water tanker capacity 5000 liters with water filter plant ₹480,118 against a ₹205,055 median for Water works in SHAHDOL (134% above, 67 peer works) | SHAHDOL(District Collector Shahdol_IDA) | Recommended | ₹4.80 L | — | +134% | 54.7 | MEDIUM |