180 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | 180 | 3 | ₹10.31 Cr | 1 | 12.5 | KANHAIYA KUMAR SINGH 48% of spend · 5 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Bidyut Baran Mahato JAMSHEDPUR | 178 | ₹10.04 Cr | 0 |
| Aditya Prasad Sitting Rajya Sabha | 1 | ₹13.00 L | 1 |
| Pradip Kumar Varma Sitting Rajya Sabha | 1 | ₹14.97 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 74 | ₹4.60 Cr | 1 |
| Roads & Paving | 62 | ₹3.53 Cr | 0 |
| Water | 15 | ₹37.13 L | 0 |
| Religious & Cultural | 15 | ₹79.12 L | 0 |
| Drainage & Sanitation | 7 | ₹44.35 L | 0 |
| Education | 4 | ₹37.19 L | 0 |
| Boundary & Protection | 2 | ₹14.72 L | 0 |
| Other | 1 | ₹5.71 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Renovation of Sitla bhavan, bhalubasa in east singhbhum, Jam Completed work has no photographic documentation on record | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Completed | ₹13.00 L | — | +128% | 58.7 | MEDIUM |
| Establishment of an Artificial Intelligence (AI) hardware an 100% similarity with another nearby work | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹14.97 L | — | 0% | 35.0 | LOW |
| Construction of club building at Kadma under Jamshedpur bloc ₹1,070,290 against a ₹570,500 median for Community Buildings works in EAST SINGHBUM (88% above, 145 peer works) | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹10.70 L | — | +88% | 31.1 | LOW |
| Construction of kitchen room in Swami Sahajanand Club buildi ₹1,002,307 against a ₹570,500 median for Community Buildings works in EAST SINGHBUM (76% above, 145 peer works) | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹10.02 L | — | +76% | 28.1 | LOW |
| Construction of 500 feet PCC road in Panchayat Gaurdeh villa 78 days beyond expected completion | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹6.49 L | 78 d | +7% | 27.0 | LOW |
| Construction of Karambandh bathing ghat in Bhurkadih village 78 days beyond expected completion | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹6.32 L | 78 d | +11% | 26.8 | LOW |
| 400 feet PCC road construction work in village Mukrudih in L 78 days beyond expected completion | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹5.79 L | 78 d | -4% | 26.3 | LOW |
| Construction work of 400 feet PCC road from old petrol pump 78 days beyond expected completion | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹5.81 L | 78 d | -4% | 26.3 | LOW |
| Construction work of guard wall from Anil Patar house to Tee 78 days beyond expected completion | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹5.72 L | 78 d | 0% | 26.3 | LOW |
| 400 feet PCC road construction work in village Ghaghra in Ma 78 days beyond expected completion | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹5.54 L | 78 d | -9% | 26.0 | LOW |
| Construction of shed (chaupal) in village Roladih in Hensda 78 days beyond expected completion | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹4.90 L | 78 d | -14% | 25.6 | LOW |
| Construction of shed (chaupal) in Upper Tola village of Mayu 78 days beyond expected completion | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹5.07 L | 78 d | -11% | 25.6 | LOW |
| Construction of a public shed in front of Panchayat Khedua v 48% of this agency's ₹77,045,972 spend went to one vendor (KANHAIYA KUMAR SINGH), across 5 vendors and 191 transactions | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹7.50 L | — | +31% | 22.3 | LOW |
| Construction of community hall at Tudi village in Gitilata P ₹818,100 against a ₹570,500 median for Community Buildings works in EAST SINGHBUM (43% above, 145 peer works) | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹8.18 L | — | +43% | 20.0 | LOW |
| Construction of public club building in front of Durga Maida ₹799,500 against a ₹570,500 median for Community Buildings works in EAST SINGHBUM (40% above, 145 peer works) | EAST SINGHBUM(DEPUTY COMMISSIONER EAST SINGHBUM_IDA) | Recommended | ₹8.00 L | — | +40% | 19.2 | LOW |