692 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | 692 | 98 | ₹17.68 Cr | 174 | 29.6 | Krupal Construction 18% of spend · 106 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Rajpalsinh Mahendrasinh Jadav PANCHMAHAL | 297 | ₹6.31 Cr | 11 |
| Parmar Jashvantsinh Salamsinh Sitting Rajya Sabha | 264 | ₹7.51 Cr | 85 |
| Jashubhai Bhilubhai Rathva CHHOTA UDAIPUR | 131 | ₹3.86 Cr | 78 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 316 | ₹7.62 Cr | 89 |
| Water | 138 | ₹1.38 Cr | 22 |
| Education | 128 | ₹3.87 Cr | 41 |
| Community Buildings | 34 | ₹1.44 Cr | 3 |
| Religious & Cultural | 20 | ₹46.67 L | 2 |
| Boundary & Protection | 18 | ₹36.29 L | 1 |
| Health | 14 | ₹1.84 Cr | 8 |
| Drainage & Sanitation | 14 | ₹31.00 L | 2 |
| Street Lighting | 6 | ₹6.75 L | 5 |
| Equipment & Vehicles | 3 | ₹22.00 L | 1 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| streetlight work from bhagyoday petrolpump to matiyafaliya p ₹200,000 against a ₹100,000 median for Street Lighting works in PANCH MAHALS (100% above, 15 peer works) | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹2.00 L | 90 d | +100% | 61.3 | MEDIUM |
| construction of boundary wall of PHC kevadiya ₹500,000 against a ₹117,452 median for Health works in PANCH MAHALS (326% above, 27 peer works) | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹5.00 L | 81 d | +326% | 60.0 | MEDIUM |
| insttalation of cctv camera at market and bhagyodaya petrolp ₹573,000 against a ₹300,000 median for Education works in PANCH MAHALS (91% above, 225 peer works) | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹5.73 L | 90 d | +91% | 59.0 | MEDIUM |
| Rathod Bhupendrasinh Arjunsih na Patel Faliyama Sarvajanik B 226 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹60,000 | 226 d | -25% | 58.2 | MEDIUM |
| Prathamik Shala thi Matajina Mandir taraf jata cc road nu ka 336 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹2.00 L | 336 d | 0% | 57.3 | MEDIUM |
| Mother Faliyama sarvajanik bor motor nu kam Tanki sahit 226 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹1.00 L | 226 d | +25% | 57.2 | MEDIUM |
| Work of Paver Block 175 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹1.00 L | 175 d | -50% | 55.8 | MEDIUM |
| Work of Paver Block 175 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹1.00 L | 175 d | -50% | 55.8 | MEDIUM |
| Work of Paver Block 175 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹1.00 L | 175 d | -50% | 55.8 | MEDIUM |
| Work of Paver Block 175 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹1.00 L | 175 d | -50% | 55.8 | MEDIUM |
| Work of Paver Block 175 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹1.00 L | 175 d | -50% | 55.8 | MEDIUM |
| Work of Paver Block 175 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹1.00 L | 175 d | -50% | 55.8 | MEDIUM |
| Work of Paver Block 175 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹1.00 L | 175 d | -50% | 55.8 | MEDIUM |
| Work of Paver Block 175 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹1.00 L | 175 d | -50% | 55.8 | MEDIUM |
| Work of Paver Block 175 days beyond expected completion | PANCH MAHALS(DISTRICT COLLECTOR PANCHMAHALS_IDA) | Recommended | ₹1.00 L | 175 d | -50% | 55.8 | MEDIUM |