263 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | 263 | 154 | ₹8.95 Cr | 5 | 13.3 | D R KUKADIA 6% of spend · 102 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Mansukhbhai Dhanjibhai Vasava BHARUCH | 260 | ₹8.64 Cr | 2 |
| Mayankkumar Nayak Sitting Rajya Sabha | 1 | ₹10.00 L | 1 |
| Parmar Jashvantsinh Salamsinh Sitting Rajya Sabha | 1 | ₹20.00 L | 1 |
| Govindbhai Laljibhai Dholakia Sitting Rajya Sabha | 1 | ₹1.20 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 145 | ₹4.40 Cr | 0 |
| Water | 29 | ₹47.17 L | 1 |
| Community Buildings | 26 | ₹95.49 L | 0 |
| Religious & Cultural | 20 | ₹91.44 L | 0 |
| Other | 18 | ₹75.23 L | 0 |
| Street Lighting | 8 | ₹28.46 L | 1 |
| Education | 6 | ₹90.99 L | 2 |
| Sports | 5 | ₹6.00 L | 0 |
| Drainage & Sanitation | 3 | ₹9.98 L | 0 |
| Boundary & Protection | 2 | ₹9.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Bharuch Jilla na balko ne Bon Condoction Machin 251 days beyond expected completion | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹1.20 L | 251 d | 0% | 55.6 | MEDIUM |
| CONSTRUCTION OF CLASS ROOMS AT SHREE KOTESWAR MAHADEV HIGH S ₹2,000,000 against a ₹300,000 median for Education works in BHARUCH (567% above, 15 peer works) | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹20.00 L | — | +567% | 46.8 | MEDIUM |
| for construction of rooms in Narmada Division Education Boar ₹1,000,000 against a ₹300,000 median for Education works in BHARUCH (233% above, 15 peer works) | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹10.00 L | — | +233% | 46.8 | MEDIUM |
| rajwadi gam bakda nu kam ₹200,000 against a ₹120,000 median for Water works in BHARUCH (67% above, 41 peer works) | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹2.00 L | 287 d | +67% | 43.5 | MEDIUM |
| bholav gam ma highmas tower ni kamgiri ₹200,000 against a ₹124,250 median for Street Lighting works in BHARUCH (61% above, 20 peer works) | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹2.00 L | 201 d | +61% | 42.1 | MEDIUM |
| tralsa (vagakhadki) comunity hall agal pevar block ni kamgir ₹500,000 against a ₹349,822 median for Community Buildings works in BHARUCH (43% above, 40 peer works) | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹5.00 L | 282 d | +43% | 37.6 | LOW |
| nabipur adivashi smashan taraf jata rasta ma pevar block ni ₹500,000 against a ₹299,263 median for Roads & Paving works in BHARUCH (67% above, 243 peer works) | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹5.00 L | 133 d | +67% | 37.1 | LOW |
| kamaliya gam bakda nu kam 287 days beyond expected completion | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹1.00 L | 287 d | -50% | 35.9 | LOW |
| kabirgam - zarna gam bakda nu kam 287 days beyond expected completion | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹1.00 L | 287 d | -67% | 35.9 | LOW |
| atkhol gam bakda nu kam 287 days beyond expected completion | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹1.00 L | 287 d | -50% | 35.9 | LOW |
| zarnavadi gam bakda nu kam 287 days beyond expected completion | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹1.00 L | 287 d | -67% | 35.9 | LOW |
| chikhli gam bakda nu kam 287 days beyond expected completion | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹1.00 L | 287 d | -50% | 35.9 | LOW |
| juni jamuni - mauza gam bakda nu kam 287 days beyond expected completion | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹1.00 L | 287 d | -50% | 35.9 | LOW |
| kavachia game gopalbhai vanvasi na faliya ma bakda nu kam 287 days beyond expected completion | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹1.00 L | 287 d | 0% | 35.9 | LOW |
| bhangori - atkhol gam bakda nu kam 287 days beyond expected completion | BHARUCH(DISTRICT COLLECTOR BROACH_IDA) | Recommended | ₹1.00 L | 287 d | -50% | 35.9 | LOW |