223 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | SURGUJA(Collector Surguja_IDA) | 223 | 76 | ₹7.55 Cr | 24 | 18.5 | STARCARE ENTERPRISES LLP 28% of spend · 37 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Chintamani Maharaj SARGUJA | 183 | ₹4.56 Cr | 1 |
| Ranjeet Ranjan Sitting Rajya Sabha | 39 | ₹2.65 Cr | 22 |
| Rajeev Shukla Sitting Rajya Sabha | 1 | ₹35.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Water | 137 | ₹2.14 Cr | 0 |
| Street Lighting | 35 | ₹1.75 Cr | 20 |
| Roads & Paving | 24 | ₹1.99 Cr | 2 |
| Community Buildings | 14 | ₹57.71 L | 1 |
| Education | 7 | ₹64.98 L | 1 |
| Boundary & Protection | 2 | ₹21.00 L | 0 |
| Religious & Cultural | 1 | ₹6.00 L | 0 |
| Sports | 1 | ₹3.00 L | 0 |
| Health | 1 | ₹5.00 L | 0 |
| Equipment & Vehicles | 1 | ₹10.00 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |
| Installation of Hybrid Solar High Mast Light 145 days beyond expected completion | SURGUJA(Collector Surguja_IDA) | Recommended | ₹5.00 L | 145 d | 0% | 51.1 | MEDIUM |