106 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | 106 | 82 | ₹7.02 Cr | 13 | 19.2 | ECONATIVE VENTURES PRIVATE LIMITED 32% of spend · 30 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Ranjeet Ranjan Sitting Rajya Sabha | 59 | ₹3.84 Cr | 11 |
| Kamlesh Jangde JANJGIR CHAMPA | 47 | ₹3.17 Cr | 2 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 44 | ₹2.84 Cr | 11 |
| Street Lighting | 24 | ₹1.34 Cr | 2 |
| Roads & Paving | 19 | ₹1.59 Cr | 0 |
| Water | 8 | ₹16.00 L | 0 |
| Community Buildings | 8 | ₹85.99 L | 0 |
| Sports | 1 | ₹10.00 L | 0 |
| Drainage & Sanitation | 1 | ₹9.99 L | 0 |
| Religious & Cultural | 1 | ₹2.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Highmast solar Street light- Two piece ₹993,000 against a ₹496,500 median for Street Lighting works in JANJGIR-CHAMPA (100% above, 36 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹9.93 L | — | +100% | 45.8 | MEDIUM |
| Highmast Solar Street light- Two Piece ₹993,000 against a ₹496,500 median for Street Lighting works in JANJGIR-CHAMPA (100% above, 36 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹9.93 L | — | +100% | 45.8 | MEDIUM |
| Installation of multigym equipment in Pre Matric Scheduled C ₹1,000,000 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (100% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹10.00 L | — | +100% | 45.8 | MEDIUM |
| Installation of multigym equipment Post Matric Scheduled cas ₹1,000,000 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (100% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹10.00 L | — | +100% | 45.8 | MEDIUM |
| Installation of multigym equipment Pre Matric Scheduled cast ₹1,000,000 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (100% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹10.00 L | — | +100% | 45.8 | MEDIUM |
| Installation of multigym equipment Pre Matric Scheduled cast ₹1,000,000 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (100% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹10.00 L | — | +100% | 45.8 | MEDIUM |
| Installation of multigym equipment Pre Matric Scheduled cast ₹1,000,000 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (100% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹10.00 L | — | +100% | 45.8 | MEDIUM |
| Installation of multigym equipment Pre Matric Scheduled cast ₹1,000,000 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (100% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹10.00 L | — | +100% | 45.8 | MEDIUM |
| Installation of multigym equipment Pre Matric Scheduled cast ₹1,000,000 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (100% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹10.00 L | — | +100% | 45.8 | MEDIUM |
| Installation of multigym equipment Pre Matric Scheduled cast ₹1,000,000 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (100% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹10.00 L | — | +100% | 45.8 | MEDIUM |
| Installation of multigym equipment Pre Matric Scheduled cast ₹1,000,000 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (100% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹10.00 L | — | +100% | 45.8 | MEDIUM |
| Installation of multigym equipment Pre Matric Scheduled cast ₹1,000,000 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (100% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹10.00 L | — | +100% | 45.8 | MEDIUM |
| Leveling of the Government School playground in Village Sing ₹997,058 against a ₹500,000 median for Education works in JANJGIR-CHAMPA (99% above, 87 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹9.97 L | — | +99% | 45.7 | MEDIUM |
| BHAWAN NIRMAN (SARASWATI SHISHU MANDIR HATARI CHAMPA ME ) ₹2,000,000 against a ₹999,000 median for Community Buildings works in JANJGIR-CHAMPA (100% above, 11 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Recommended | ₹20.00 L | 42 d | +100% | 39.7 | LOW |
| Highmast Solar Street light- Two Piece. ₹993,000 against a ₹496,500 median for Street Lighting works in JANJGIR-CHAMPA (100% above, 36 peer works) | JANJGIR-CHAMPA(DISTRICT COLLECTOR JANJGIR CHAMPA_IDA) | Completed | ₹9.93 L | — | +100% | 37.5 | LOW |