238 works across 1 implementing agency, recommended by 3 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | 238 | 174 | ₹10.46 Cr | 136 | 40.8 | CHANCH PRO ENGINEERS 33% of spend · 9 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Arun Bharti JAMUI | 226 | ₹10.19 Cr | 135 |
| Shambhu Sharan Patel Sitting Rajya Sabha | 9 | ₹10.59 L | 0 |
| Bhim Singh Sitting Rajya Sabha | 3 | ₹15.69 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 175 | ₹6.09 Cr | 135 |
| Street Lighting | 23 | ₹2.17 Cr | 0 |
| Roads & Paving | 15 | ₹58.67 L | 0 |
| Other | 10 | ₹13.09 L | 0 |
| Equipment & Vehicles | 7 | ₹1.05 Cr | 0 |
| Community Buildings | 4 | ₹20.65 L | 1 |
| Water | 2 | ₹5.93 L | 0 |
| Religious & Cultural | 1 | ₹2.94 L | 0 |
| Drainage & Sanitation | 1 | ₹13.29 L | 0 |
Patterns across an agency’s whole book of work. None of these move any individual work’s score.
The whole population fails the textbook test — the median agency scores 6.2 where Nigrini calls 1.5 nonconformant — because MPLADS amounts are capped, rounded and repeated by design. This ranks agencies against each other, not against the law. It is the weakest signal here and is never evidence on its own.
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction work of 20 feet x 15 feet covered Community Cha 402 days beyond expected completion | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Recommended | ₹5.30 L | 402 d | 0% | 58.0 | MEDIUM |
| Installation of indoor gym equipment in school Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of indoor gym equipment in school Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of indoor gym equipment in school Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Indoor multi gym equipment in school Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Indoor multi gym equipment in school Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Multi gym equipments in School. Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Multi gym equipments in School. Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Multi gym equipments in School. Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Multi gym equipments in School. Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Multi gym equipments in school Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Multi gym equipments in school Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Multi gym equipments in school Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Multi gym equipments in school Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |
| Installation of Multi gym equipments in school Completed work has no photographic documentation on record | JAMUI(DISTRICT PLANNING OFFICER JAMUI_IDA) | Completed | ₹17.00 L | — | +1600% | 53.4 | MEDIUM |