90 works across 1 implementing agency, recommended by 5 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | GOALPARA(Deputy Commissioner Goalpara_IDA) | 90 | 7 | ₹8.79 Cr | 5 | 27.1 | Shyama Gaon Bazar to Shyama Gaon Field 8% of spend · 71 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Bijuli Kalita Medhi GUWAHATI | 37 | ₹3.43 Cr | 2 |
| Rakibul Hussain DHUBRI | 37 | ₹1.93 Cr | 2 |
| Birendra Prasad Baishya Sitting Rajya Sabha | 8 | ₹1.97 Cr | 0 |
| Rwngwra Narzary Sitting Rajya Sabha | 4 | ₹96.00 L | 0 |
| Kanad Purkayastha Sitting Rajya Sabha | 4 | ₹50.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 29 | ₹1.31 Cr | 2 |
| Roads & Paving | 21 | ₹5.16 Cr | 0 |
| Boundary & Protection | 16 | ₹65.50 L | 0 |
| Education | 11 | ₹60.50 L | 2 |
| Religious & Cultural | 6 | ₹44.00 L | 1 |
| Health | 3 | ₹27.00 L | 0 |
| Drainage & Sanitation | 3 | ₹26.00 L | 0 |
| Equipment & Vehicles | 1 | ₹9.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction for common sitting area at dhunubhaga . ₹1,200,000 against a ₹480,200 median for Community Buildings works in GOALPARA (150% above, 37 peer works) | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹12.00 L | 385 d | +150% | 55.0 | MEDIUM |
| Construction of Community Hall at Sarapara Village , Bardam ₹1,000,000 against a ₹480,200 median for Community Buildings works in GOALPARA (108% above, 37 peer works) | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹10.00 L | 165 d | +108% | 53.0 | MEDIUM |
| Construction of Boundary wall along with Iron gate near Naba ₹2,000,000 against a ₹500,000 median for Religious & Cultural works in GOALPARA (300% above, 8 peer works) | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹20.00 L | — | +300% | 50.0 | MEDIUM |
| Construction of Science Laboratory Building at Goalpara Coll ₹1,000,000 against a ₹490,100 median for Education works in GOALPARA (104% above, 18 peer works) | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹10.00 L | — | +104% | 47.5 | MEDIUM |
| Construction of Science Laboratory Building at Goalpara Coll ₹1,000,000 against a ₹490,100 median for Education works in GOALPARA (104% above, 18 peer works) | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹10.00 L | — | +104% | 47.5 | MEDIUM |
| Construction of additional room near Kubereswar Mandir at Mo 333 days beyond expected completion | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹6.00 L | 333 d | +20% | 39.9 | LOW |
| Porviding One Abbulance Facilities for BPHCs in Jaleswar Mod 183 days beyond expected completion | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹9.00 L | 183 d | 0% | 39.0 | LOW |
| Porviding One Abbulance Facilities for Simlatala Char Primar 183 days beyond expected completion | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹9.00 L | 183 d | 0% | 39.0 | LOW |
| Constraction of toilet blocks at Mespara Madhachal Rabha Sam 385 days beyond expected completion | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹4.00 L | 385 d | 0% | 39.0 | LOW |
| Construction of open Community hall near Bisahari than at Ra 333 days beyond expected completion | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹3.50 L | 333 d | -27% | 38.8 | LOW |
| Construction of open Community Hall at Jyotigaon Kanaklata M 333 days beyond expected completion | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹3.50 L | 333 d | -27% | 38.8 | LOW |
| Construction of community hall at Mujkuri Rajohuwa Namghar a 333 days beyond expected completion | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹3.50 L | 333 d | -27% | 38.8 | LOW |
| Construction of Open Community Hall at Tarun Sangha , Mornai 333 days beyond expected completion | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹3.50 L | 333 d | -27% | 38.8 | LOW |
| Construction open Cummunity hall at Lokpriya gopinath bordol 333 days beyond expected completion | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹3.50 L | 333 d | -27% | 38.8 | LOW |
| Construction of open community hall at near Bakaitary Anchal 333 days beyond expected completion | GOALPARA(Deputy Commissioner Goalpara_IDA) | Recommended | ₹3.50 L | 333 d | -27% | 38.8 | LOW |