30 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) 1 high risk | 30 | 0 | ₹3.00 Cr | 14 | 40.2 | Dhwrwmsing Baro 34% of spend · 5 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Joyanta Basumatary KOKRAJHAR | 15 | ₹1.55 Cr | 4 |
| Rwngwra Narzary Sitting Rajya Sabha | 8 | ₹72.00 L | 8 |
| Dilip Saikia Darrang-Udalguri | 5 | ₹12.50 L | 0 |
| Pramod Boro Sitting Rajya Sabha | 2 | ₹60.00 L | 2 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 16 | ₹1.55 Cr | 8 |
| Religious & Cultural | 6 | ₹30.00 L | 0 |
| Community Buildings | 3 | ₹22.50 L | 2 |
| Education | 2 | ₹22.00 L | 2 |
| Water | 2 | ₹60.00 L | 2 |
| Drainage & Sanitation | 1 | ₹10.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of RCC Bridge at Atiabari Golbil road, Barimaka ₹1,500,000 against a ₹1,000,000 median for Roads & Paving works in BAKSA (50% above, 46 peer works) | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹15.00 L | 451 d | +50% | 70.8 | HIGH |
| Construction of Boundary wall at Uttar Salbari L.P. School, Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹12.00 L | 448 d | 0% | 70.0 | MEDIUM |
| Construction of Bhogpara Brahmapur Mongolian Afad community Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹10.00 L | 447 d | 0% | 69.0 | MEDIUM |
| construction of Culvert at Barfena Pathar Kalbari under Jala Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹10.00 L | 448 d | 0% | 69.0 | MEDIUM |
| Constructionn of Anjalu Sanga Community Hall at Laokhata vil Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹10.00 L | 448 d | 0% | 69.0 | MEDIUM |
| Construction of RCC Box Culvert at Jakhilirpar village under 451 days beyond expected completion | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹5.00 L | 451 d | -50% | 65.3 | MEDIUM |
| construction of RCC Box Culvert at Bathouguri ( Bartari) vil 451 days beyond expected completion | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹5.00 L | 451 d | -50% | 65.3 | MEDIUM |
| Construction of RCC Box Culvert at Bagarpara(Bunmaja) villag 451 days beyond expected completion | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹5.00 L | 451 d | -50% | 65.3 | MEDIUM |
| Construction of road at Simlaguri village from Paniram house ₹1,500,000 against a ₹1,000,000 median for Roads & Paving works in BAKSA (50% above, 46 peer works) | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹15.00 L | 168 d | +50% | 47.2 | MEDIUM |
| Solar-powered drinking water for Monipur village, Dhamdhama Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹30.00 L | — | 0% | 45.0 | MEDIUM |
| Solar powered drinking water facility for Subankhata village Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹30.00 L | — | 0% | 45.0 | MEDIUM |
| Construction of additional classroom at Dakhin Bijni Degree 168 days beyond expected completion | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹10.00 L | 168 d | 0% | 43.8 | MEDIUM |
| Construction of road at South Barkhuchijar Bathou Mandir to 168 days beyond expected completion | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹4.00 L | 168 d | -60% | 41.2 | MEDIUM |
| Construction of road at Dangrigaon St. Matthew Church road u 168 days beyond expected completion | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹4.00 L | 168 d | -60% | 41.2 | MEDIUM |
| Construction of open stage near Chaulkara Anchalic Mandir un ₹1,000,000 against a ₹300,000 median for Religious & Cultural works in BAKSA (233% above, 9 peer works) | BAKSA(DEPUTY COMMISSIONER BAKSA_IDA) | Recommended | ₹10.00 L | — | +233% | 36.4 | LOW |